Planning and timelines · 6 min read
Planning a Summer Lab Upgrade: From Budget to Handover
A stage-by-stage plan for upgrading school science labs in the summer break: audit, design, budget approval, ordering, installation and handover.
By Charleston Education Team · Published

A summer lab upgrade is planned backwards from the start of term. The date that matters most is the furniture order, because lab furniture is made to order and has to be shipped. How far ahead that order needs to go in depends on the range you choose and on shipping at the time, so start the audit and design early and agree the dates with your contractor before your board sets next year's spending.
The timeline at a glance
| Stage | What it is | What happens | Who is involved |
|---|---|---|---|
| 1 | Audit and design | Site visit, survey of services, 3D concept, budget for your board | Head of science, facilities manager, bursar, designer |
| 2 | Sign-off and order | Final design approved, contract signed, furniture ordered | Bursar, head, contractor |
| 3 | Site preparation | Shipping, detailed setting out, permits, programme agreed | Contractor, facilities manager |
| 4 | Build and install | Strip out, services, flooring, furniture installation, testing | Contractor, facilities manager |
| 5 | Handover | Snagging, safety checks, training, documentation | Head of science, technicians, facilities manager |
Every project runs at its own pace. The size of the rooms, the furniture range, shipping and what is found on site all change the timing, so treat this as an order of steps, not a fixed calendar.
Audit and design
Most of the important decisions are made here, and this is also where schools most often lose time.
Start with an audit
A good audit covers:
- Existing services: where the gas, water, drainage and electrical supplies are, and what condition they are in.
- Building constraints such as columns, windows, ceiling height, floor construction and access for deliveries.
- How the rooms are used: class sizes, subjects, practical frequency, storage and prep room workflow.
- Safety: gas isolation, emergency stops, eye wash, fume cupboards and exits, checked against current guidance.
Our guide to school science lab design standards explains the guidance a good audit should check against.
Agree the brief
Get your head of science, technicians and facilities manager in the same room. Agree:
- How many labs and which subjects.
- Preferred layout (island, perimeter, or flexible).
- Fume cupboard needs. See Fume Cupboards for Schools: Ducted vs Ductless.
- Storage and prep room changes.
- What must stay, and what can change.
Get a 3D concept and budget
A 3D concept lets staff and governors see the proposed room before anything is ordered. With it you need a budget range broken down into furniture, services, building work, shipping and VAT. For more on cost drivers, read What Does a School Renovation Cost?.
Present to your board
Timing the board paper is often the hardest part for a bursar. If the budget is not approved before the next financial year's spending is set, the project slips by a year. Aim to present:
- The 3D concept.
- A fixed quote or a tightly ranged budget.
- Payment milestones.
- A draft programme, with the date the furniture needs to be ordered.
Sign-off and furniture order
Why the order date matters
Lab furniture from SB Labs (UK) and BFX (Australia) is made to order and shipped to Thailand. Manufacture, shipping and customs clearance take time, and that time varies by range, by order and by season. If the order goes in late, the furniture may not arrive before the install window closes. Our own range, from manufacturers in China and Thailand, has different timing again. We confirm the timing for the range you choose when the order is placed.
What to finalise
- Final layout drawings approved by the head of science
- Worktop material and colour chosen
- Services positions confirmed at each station
- Fume cupboard type and position confirmed
- Contract signed with a fixed price
- Deposit paid (with Charleston, 60% on sign-off)
- Install dates agreed with the school calendar
Late changes
Changes after the order are possible but expensive. Moving a sink after the bench is manufactured may mean re-ordering a unit. Get the layout right before you sign.
Site preparation while furniture ships
While the furniture is in transit, the contractor should be preparing the site.
- A week-by-week programme for the install, shared with the facilities manager.
- Any building or utility approvals needed under Thai rules.
- Delivery routes, storage for furniture on arrival, working hours and security.
- Who empties the labs and stores chemicals and equipment. Plan this with your technicians before the last day of term.
- Safe storage for chemicals during the works, with responsibility agreed in writing.
Build and install
The on-site period typically runs in this order:
- Strip out of old benches, services and finishes.
- First fix services: new gas, water, drainage and electrical routes in floors, walls or ceilings.
- Building work, including any wall changes, ceiling work and fume cupboard ductwork.
- Chemical-resistant, non-slip flooring, laid before the furniture goes in.
- Installation of benches, storage, worktops and fume cupboards.
- Second fix services: taps, gas outlets, sockets and emergency controls connected.
- Gas, electrical and fume cupboard testing and certification.
- A full clean before handover.
How long this takes on site depends on the scope, the condition of the building and access.
Keeping the project on track
- Weekly progress reports in English and Thai, with photos.
- A single point of contact at the school and at the contractor.
- Early warning of any problem found behind walls or under floors, with options and costs before work continues.
Handover and setup
Plan the handover as carefully as the build, and walk through it with the people who will use the rooms.
Handover checklist
- Snagging walk-through with the head of science and facilities manager
- All snags fixed or listed with agreed dates
- Gas, electrical and fume cupboard test certificates provided
- Emergency gas isolation and emergency stop demonstrated to staff
- Technician training on fume cupboards, services and furniture care
- Operation and maintenance information, warranties and drawings handed over
- Defects period and contact details for warranty claims confirmed
Leave time before the first day of term for technicians to set up equipment and chemicals. A room that is "finished" on the last day before term is not ready for teaching.
If you have started late
Starting late does not always mean waiting a full year. Options to discuss with your contractor include:
- Phase the work: services, flooring and building work this summer, with the furniture installed in a shorter break later in the year.
- Source storage and loose furniture locally on a shorter lead time, and let the imported benches follow.
- Reduce the scope: upgrade one lab this summer and plan the rest properly for the following year.
Each option costs something in money or disruption, so weigh it against starting the full project a year later with a proper plan.
What usually goes wrong
| Problem | Cause | How to avoid it |
|---|---|---|
| Project slips a full year | Budget not approved in time | Start the audit early and present to the board early |
| Furniture arrives late | Order placed too late | Agree the order date at sign-off and keep to it |
| Cost increases on site | Hidden conditions not surveyed | Survey services and structure during the audit |
| Lab not usable on day one | No time left for setup | Plan handover before the end of the summer break |
| Staff unhappy with layout | Science team not involved early | Include the head of science from the first meeting |
Start your plan early
The earlier the audit and design start, the more choice you have on furniture and install dates. A free Facilities Audit gives you an on-site walk-through, a 3D concept and a budget range with a project plan you can take to your board. Find out more about our science lab design and build service.
Related service: Science Labs

About the author: Charleston Education Team
The Charleston Education team designs, supplies and installs science labs and learning spaces for international schools across Thailand, working with SB Labs (UK), BFX (Australia) and our own furniture range.